Resource Cost

For some organizations, resources costs are primary costs, and sometimes the only cost, so these need to be closely monitored.

resource cost

Task Work

In the Task Work report, the time amount of total work, actual work, and remaining works are displayed for all sub-tasks.

The following are formulas to calculate different types of cost:

  • Actual Work = Progress*Work
  • Remaining Work = (1 - Progress) * Work
task work