Critical Tasks

It has to be clear that the word “Critical” does not mean that the task is complex, important or need to be closed, monitored, but the focus is that the task will affect the project's finish date.

critical tasks

Delay Tasks

In the Delay Tasks report, Tasks that have been delayed in comparison with the current date are displayed.

delay tasks

Behind Tasks

If a task’s completion date exceeds its baseline finish date, then it is a Behind Task.

Click the Behind Tasks buttonbehind tasks button on the Reports tab to view the report of behind tasks in the project.

behind tasks